1HT Engineering, Inc., Grand Rapids, USA., 2TC Energy, Chicago, USA., 3BP, Chicago, USA., 4ROSEN, Houston, USA
1HT Engineering, Inc., Grand Rapids, USA. 2TC Energy, Chicago, USA. 3BP, Chicago, USA. 4ROSEN, Houston, USA
Abstract
This paper presents the lessons learned by the team that planned, designed, and managed a project to run gauge pigs and in-line inspection (ILI) tools through an idled pipeline. The runs covered the multiple piggable segments of a nitrogen-filled 450-mile liquid hydrocarbon product line in preparation for its return to service. Running ILI tools in lines previously in liquid service and subsequently filled with nitrogen presents challenges. This study provides insight into the pipeline system characteristics, including human factors, that must be addressed to achieve successful tool runs in nitrogen.
For this project, the team synthesized requirements from management, technical, and operations stakeholders, and developed an execution plan. During planning, the team built a numerical hydraulic model to calculate the nitrogen flow rates and pressures required to successfully run the pigs. The team worked with local operations personnel and the ILI vendor to develop detailed work procedures. During operations engineers worked on site tracking procedure completion and monitoring operating conditions. Two ILI runs failed to meet acceptance criteria, one due to abnormal ILI tool drive cup wear and one due to inadequate nitrogen control procedures. The team identified the problems and designed solutions. After each operation, the team captured lessons learned and updated subsequent procedures accordingly.
The execution plan provided the company’s management with confidence that the project could be completed safely. The numerical hydraulic model allowed the team to optimize nitrogen injection and release locations, plan injection and release operations, and verify that pressures and pig speeds could be kept within acceptable operating ranges. The solutions for the failed runs (a revised ILI tool drive cup design and a new procedure for nitrogen control) prevented recurrence of the problems and resulted in successful reruns. The lessons learned process allowed the team to improve its numerical model and human performance as the project progressed. By monitoring and analyzing the operating conditions in real time, the engineers were able to provide the project manager with the information and recommendations needed to run the operations safely and recognize emerging problems quickly.
Pipeline operators are frequently faced with the need to respond to changing market conditions and must be able to safely inspect idled lines in a timely manner. The results of this study provide operators with insight into the factors that must be addressed to achieve successful tool runs in nitrogen. These results complement the findings of Bonner, D., Greig, A., Lindner, H., Becker, J., Roulston, B., (2018, September 24-28). REACTIVATING A LEGACY PIPELINE – SIMULATING ILI RUN BEHAVIOR, OPERATION OPTIMIZATION, AND PROJECT CHALLENGES. International Pipeline Conference, Calgary, Alberta, Canada.