A case study was conducted on a sour gas service pipeline with high H2S concentration. The aim of the study was to evaluate the current condition of the pipeline and to provide a solution to perform the In-line Inspection (ILI) base run. The sour gas service pipeline was constructed in 2012, has been operating since 2013, and has over 50 KM in length with a size of 20" in diameter. 

As part the commissioning, a caliper run was conducted to assess the pipeline’s internal diameter, which revealed that there were no restrictions or dents in the line. After the pipeline was commissioned, ILl runs were scheduled as per the standard requirements, to inspect the newly commissioned pipeline to ensure full integrity. A gauging run was conducted to assure pipeline mechanical readiness for the ILI run. 

The gauging run resulted in an unsuccessful run due to considerable damages in the tool and huge amount of debris (more than 1000 kg). A following gauging run was conducted after assuring that all valves were fully opened, which resulted in an unsuccessful with the same damage profile as the previous run.

Given the unsuccessful gauging runs, a caliper run was conducted to identify the obstacle. The caliper tool was retrieved with severe damages and was inconclusive with regards to the internal obstruction.

A comprehensive assessment on the pipeline was conducted to evaluate the causes of the damages, which revealed that the damage was due to hardened debris within the pipeline as a consequence of improper chemical cleaning that was implement after the line was in-service.

The assessment recommended a cleaning campaign with specialized spring-loaded cleaning tools with magnets followed by a caliper tool. The cleaning campaign contained a minimum of thirty back-to-back aggressive cleaning runs. After completing the cleaning campaign, the caliper tool was conducted successfully and the internal restriction was negotiable by utilizing the 18/20" ILl tool, which was conducted successfully. This cleaning campaign resulted in a successful revalidation of the pipeline.